NPK GRANULAR II PT. PUPUK KUJANG

Client : PT. PUPUK KUJANG CIKAMPEK
Location : CIKAMPEK
Period : 2014
Outline of Project

Establishment of NPK Granular Plant Cap. 1 x 100.000 MTPY

Landscape, mountains

PROYEK PENGADAAN JASA UREA BULK STORAGE-6 & CONVEYOR SYSTEM (UBS-6 & CS) PT. PUPUK KALTIM

Client : PT. PUPUK KALIMANTAN TIMUR
Location : BONTANG - KALIMANTAN TIMUR
Period : 2014
Outline of Project

Establishment of Bulk Storage Facilities and Conveyor System for Fertilizer on Turnkey Basis

Landscape, mountains

NEW GATHERING STATION AT NIRU STRUCTURE

Client : PT. Pertamina EP
Location : Niru - South Sumatra
Period : 2011
Outline of Project

Construction the niru gathering station facility to handle oil production from 27 well and 2 injection wells at niru area. The capacity of each well is predicted around 850 BFPD, total fluida is amount 23.000 BFPD

Scope of Work

Procurement and Construction

Landscape, mountains

TERMINAL FACILITIES & PIPELINE C O N S T R U C T I O N F O R G R E S I K TERMINAL (P ACKAGE 2)

Client : PT Shell Indonesia
Location : Gresik, Jatim - Indonesia
Period : 2009
Outline of Project

The Project is desirous of engaging a service provider to provide works related to terminal piping and pumping f a c i l i t y, d o c k l i n e s , m a r i n e l o a d i n g a r m , p i g launching /receiving facility , truck loading, fire fighting works, buildings and shelters and associated electrical, instrumentation and civil works.

Scope of Work

Procurement, Construction and Commissioning for the T erminal Facility and Pipeline Construction

Landscape, mountains

NPK GRANULATION III & IV CA

Client : PT . Petrokimia Gresik
Location : Gresik, Jatim - Indonesia
Period : 2009
Outline of Project

Built NPK-basic-Fertilizer Plant, 2x100.000 Production Capacity , starting from new m handling, Granulation Process, product handli bagging/packaging

Scope of Work

Engineering, Procurement and Construction

Landscape, mountains

NEW FEED STOCK TRASFER FACILITY

Client : PT Cabot Indonesia
Location : Cilegon, Banten - Indonesia
Period : 2004
Outline of Project

Installation of a new carbon black feed stock facility consisting of un-loading facility at port of Cigading includes pump house, booster pump, recovery ponds an feed stock pipeline from jetty to PT Carbon Indonesia's Plant at Krakatau Industrial Estate Cilegon. Total length of 8 km pipeline consisting at +2km above ground and +6km ground of 20" - API5L Gr. Steel Pipe, Launcher and receiver are installed.

Scope of Work

Engineering, Procurement, Construction and Commissioning.